One Stop Center Garage

Location:
Dayton, Ohio

Owner:
City of Dayton

Engineer:
O&S Associates

Contract Amount:
$500,000

Completion Date:
May 2004

Work Description:
After the project was competitively bid and a repair contract was awarded to CPS, we presented our value engineering ideas to the City of Dayton & their Structural Engineer. We recommended replacing all existing precast tees and wall panels on the 30-year old structure in lieu of patching the existing concrete. Other site improvements included installing new plumbing, light fixtures, decorative tube railing and security fencing. New caulking, expansion joints and a protective traffic membrane were also installed. CPS completed the new garage construction for the same cost as the scheduled renovation.